Do Well-Drafted Redevelopment Agreements Protect Flat Owners? No!
29th
May, 2016, Mumbai: If the Development Agreement is well drafted, then
flat-owners are safe, right? Well-drafted contract documents protect
the flat-owners if the builders don't honour the contract, right? NO,
WRONG! A well-drafted agreement doesn't give you automatic
protection; it gives you the LEGAL RIGHT TO FIGHT to dismiss or
penalize a non-performing builder... but you will definitely have to
wage
a legal battle, and your society will be your enemy, not your
supporter. Why?
REASON
NO. 1: NO SUO MOTU ENFORCEMENT. Law enforcement agencies and courts
are not required to act suo
motu to
defend your individual
legal rights. Therefore, you have to go to great lengths to convince
enforcement agencies and/or courts that (a) you have a certain right
under the contractual agreement (b) your right has been violated and
(c) you (and not just your society) are a party to the contract. Each
of these points have to be proved by you, otherwise your complaint is
summarily dismissed. Enforcement agencies and courts are not
sympathetic to you; at best, they are indifferent, and at worst, they
are biased in favour of builders.
REASON
NO. 2: FLAT OWNER IS NOT A PARTY IN DEVELOPMENT AGREEMENT. You, the
flat-owner, are not the "society" within the meaning of the
law. Only the society i.e. the managing committee and more
particularly, the office-bearers, have authority to enforce the
contract signed with the builder, because the society has signed the
contract with the builder.
REASON
NO. 3: SOCIETY IS THE LEGAL OWNER OF YOUR FLAT. The law does not
recognize you as the "owner" of your own flat; the
cooperative housing society is the collective owner of the entire
building and compound, and you are only enjoying your flat by virtue
of being a member. Therefore, in the eyes of the law, you generally
have no "right" to go to court for the enforcement of a
contract between the society and the builder.
REASON
NO. 4: POLITICS IS NECESSARY. You can only derive your "legal
right" with the support of the society. Therefore, you should
earn a "political right" to speak and argue. If you are
alone or in a tiny minority, or if you are easily silenced, then you
have no political right, even if what you say is 100% true. To
get justice, you must gather support from other members. If
the society's office-bearers are unwilling to impose penalties,
invoke the bank guarantee, or cancel the builder's contract, then
you, the ordinary members, are mostly powerless. Getting the builder
dismissed by the society is a political battle rather than just a
judicial battle. This battle has to be fought in general-body
meetings, and in the minds and hearts of the office-bearers and
general body members.
REASON
NO. 5: REDEVELOPMENT IS INHERENTLY UNSAFE. A housing society entering
redevelopment is like an out-of-control passenger bus with an
alcholic driver drinking vodka. Even if everything is perfect at the
start of the journey, things can go rapidly downhill at any turn. As
a passenger, you may clearly see things going wrong, but you are not
in a position to turn the steering wheel or press the brakes.
THE
CASE OF KUNDAN APARTMENT, JOGESHWARI EAST
There
are many lessons to be learned from the experience of Kundan
Apartment, a small building with 15 members in Jogeshwari East, stuck
since 2010 due to non-performance of Tanna Developers.
Tanna
Developers (or Tanna Realtors as per this
website)
is a partnership firm headed by managing partner Pathik Tanna and
represented by Chartered Accountant Jignesh Tanna.
Without
verification of Tanna Developers' credentials or following 79A
Guidelines, the society appointed Tanna Developers in 2010. Tanna
applied to MCGM's Building Proposal Department and got the IOD
(Intimation Of Disapproval) in October 2010. And after that, the
builder just froze. No actions whatsoever. Zero. So,
five of the 15 flat owners, in view of the builders' continuous
non-performance over six years, want to oust them.
Redevelopment is inherently painful, like getting your teeth pulled without anesthesia! |
CLAUSES
FAVOURABLE TO FLAT-OWNERS
1)
Kundan Apartment'
LOI says: "redevelopment
work shall be completed within 18 months from the date of
IOD/Commencement Certificate.
On
failure the Letter Of Intent shall stand withdrawn and the developer
shall not be entitled to claim anything from the society."
Another clause says, "TDR
shall be purchased in the name of the society, and upon termination
of the Development Agreement/MOU, the said TDR shall be the property
of the society". Read
para
h of LOI:
2)
Stamped and registered DA upholds these clauses. DA confirms that
terms and conditions are "more particularly recorded in the
Letter Of Intent and the Memorandum Of Understanding". Read
para
Y of DA
.
3)
DA says that
"Society...
will hand over vacant and peaceful possession of all their respective
tenements to the developers... within 15 days from the date of
Commencement Certificate."
Read
para
3A of DA.
4)
Bank guarantee mentioned in DA is Rs 50 lakhs – less than market
price of even one flat. DA says that bank
guarantee can be invoked by society "on
demand without demur and enforceable on the certificate of the said
society to the concerned bankers that the developers have not
completed the construction within the total period of 24 months..."
Read
para
23 of DA.
WHY
THIS IS GOOD FOR FLAT-OWNERS
a)
The society has the upper hand and the contract is subject to a tight
deadline. The clauses clarify that Tanna may suffer major losses due
to dismissal, forfeiting the cost of TDR, permissions, sanctioned
plans, incomplete construction etc. Tanna will not be entitled to
claim anything from the society.
b)
The 18-month deadline for redevelopment is repeatedly stressed. The
bank guarantee can be revoked if the builder does not complete the
building in 24 months.
c)
DA specifies that society members will give vacant possession only
after the Commencement Certificate (CC) is received.So flat owners
are still in possession of their own houses – a huge relief.
LOOPHOLES
FAVOURING THE BUILDER
a)
Development Agreement defines the deadline as 18 months from the date
of "IOD-CC". The loophole is that IOD-CC is not a single
certificate of permission, IOD (Intimation Of Disapproval) and CC
(Commencement Certificate) are two separate permissions. The builder
is required to fulfill dozens of conditions specified in the
IOD
in order to get CC. Tanna Developers, who failed to perform the
necessary actions to procure the commencement certificate, can argue
that because they did not get CC, the 18-month clock has not started
ticking till date.
Counter-argument
no. 1: Whose
duty is it to fulfill the IOD conditions and procure the CC? The
builder's. The builders' non-performance has resulted in their not
getting CC... and therefore, they cannot use non-arrival of CC as an
excuse.
Counter-argument
no. 2: The
validity period of the IOD is two years. Tanna Developers was
supposed to get CC before the IOD expired on 18th
October 2012. He did not get CC, but if we take the last date of IOD
validity, and count 18 months from there, the deadline for completing
the redevelopment would expires in April 2014.
Since they hadn't even commenced redevelopment on that date, they
breached the contract, and LOI automatically stands withdrawn.
But
only five of the society's 15 members are speaking up against the
builders. As a whole, the society has no political will to hold the
builders accountable!
b)
The society cannot invoke the bank guarantee because Tanna
Developers have not furnished the bank guarantee till date, six years
after signing the agreement.
Far from telling him to furnish the amount,
the managing committee held a meeting in 2015 where it agreed to the
builder's demand to reduce the bank guarantee to Rs 21 lakhs! Unless
the society i.e. managing committee, certifies that the builder has
failed to meet contractual deadlines, nobody else has the full legal
authority to say
so. Thus, the Tanna Developers may go on delaying with the managing
committee's blessings!
BUILDER
HAS HIJACKED SOCIETY'S RECORDS!
Kundan
Apartment has a huge problem. With the connivance of the elected
managing committee, the builder has seized control of the society's
entire records from 1978 till date -- bank account books, minutes
books, share register, nomination register etc, society registration
certificate, bye-laws... the whole bundle! Therefore, unable to
submit the society's records for inspection, the managing committee
was dismissed by the Deputy Registrar of Cooperation in February
2015, and an administrator was appointed. The dismissed managing
committee still did not hand over its documents to the administrator.
In July 2015, the Deputy Registrar passed orders for
search-and-seizure of the documents from the managing committee
members, and requested police force for this. In October, the
managing committee handed over a tiny fraction of the records and
the administrator wrote to Jogeshwari Police Station that their
assistance was not required. Then the Deputy Registrar developed
amnesia. In response to correspondence from the dissenting society
members, he started asking, "What documents? In whose custody?"
Three
of the five members opposing the builder were briefly appointed by
the Deputy Registrar as the Authorized Committee. Despite their best
efforts, the missing papers did not emerge. Within three months,
elections were ordered to be held, and the former managing committee
is back in the driver's saddle on current date. So, without the
society's essential records, how to go to court? The society and its
members are handicapped.
CURRENT
STATUS
While
they were in the Authorized Committee, the dissenting members served
Tanna Developers a
Legal Notice
that pointed out that as per the clauses of the DA, LOI etc, their
contract automatically lapsed in April 2014, upon expiry of the
maximum allowable period within which the construction was to be
completed. It can of course be argued that the Authorized Committee
is not the elected managing committee of the society, and cannot
serve such a notice. But it can be argued on the other side that the
words "On failure, the Letter Of Intent stand withdrawn and the
Developer shall not be entitled to claim anything from Society"
have an automatic effect, and therefore, no fresh resolution or even
legal notice of the society was needed to give effect to these words.
At
present, neither side is talking to the other. In this atmosphere of
mistrust and vengefulness, the residents of Kundan Apartment are
anxiously awaiting another monsoon that will drench its cracked RCC
beams, columns and plaster. The elected managing committee, which
covers the structure with tarpaulin in some monsoons, seems inclined
to allow the building to get thoroughly soaked this year, as if to
say, "If you don't want Tanna Developers, we can all go to
hell".
The
sad story of Kundan Apartment will not end until the society pulls
itself from the grip of this builder, unites its 15 members and calls
for fresh tenders from its redevelopment.
ISSUED
IN PUBLIC INTEREST
By
Krishnaraj Rao
9821588114
krish.kkphoto@gmail.com
Comments
Post a Comment